ACTIVITIES REPORT
Partners' Institution:
Foundation of Cultural and Business Potential of Civil Society (FDCBPCS)
Project's period (from/to):
01 January 2015 - 30 December 2016
Activity concerned:
Transversal Activity 3: Quality and Monitoring Plan

Objectives of activities carried out:
The Quality Assurance process will include both an internal and an external evaluation as well as on the production of a Quality Plan.

The quality control approach also includes a strategy for the control on the budget and the production of a Financial Manual.

Finally, the potential risks have been identified and a strategy to prevent and, where necessary, resolve them has been identified.

All partners will be actively involved in the activity to ensure the quality of the project, as well as its monitoring and evaluation.
Also an external evaluator will be involved.

Each partner will provide:
- 1 progress and 1 final evaluation questionnaire filled in
- 1 progress and 1 final national evaluation report

Description of activities carried out:
Project meetings evaluated.Progress evaluation report completed and submitted.

Outcomes:
4 evaluation questionnaires about the meetings filled in from representatives of FDCBPCS. Progress and final evaluation reports completed and submitted on time.

Evaluation of the work undertaken:
The work under this TA is evaluated as satisfactory.